VW Passat repair+ 1. Ekspluatatsiiya of the car + 2. Maintenance - 3. Engines + 3.1. Petrol engines of configuration of R4 + 3.2. Petrol engine of configuration of VR6 - 3.3. Diesel engines 3.3.1. Technical characteristics 3.3.2. General information 3.3.3. Installation of the piston of the cylinder No. 1 in VMT 3.3.4. Compression check in cylinders 3.3.5. Gear belt of a drive of GRM 3.3.6. Mechanism of a tension of a gear belt 3.3.7. Gear pulley of a camshaft 3.3.8. Gear pulley of a cranked shaft 3.3.9. Pulley of an intermediate shaft 3.3.10. Belts of a drive of auxiliary units 3.3.11. Cover of a head of the block of cylinders 3.3.12. Replacement of an epiploon of a camshaft 3.3.13. Replacement of an epiploon of an intermediate shaft 3.3.14. Replacement of epiploons of a cranked shaft 3.3.15. Replacement of an epiploon of a forward cover of a cranked shaft 3.3.16. Head of the block of cylinders 3.3.17. Check of work of hydraulic pushers 3.3.18. Flywheel 3.3.19. Replacement of support of the power unit 3.3.20. Oil case 3.3.21. Oil pump 3.3.22. Top casing of the AFN engine 3.3.23. System of prestarting heating of diesel engines 3.3.24. Glow plugs + 4. Cooling system + 5. Power supply system + 6. Ignition system + 7. Coupling + 8. Transmission + 9. Drive of forward wheels + 10. Suspension brackets + 11. Steering + 12. Brake system + 13. Wheels and tires + 14. Systems of heating, ventilation and conditioning + 15. Electric equipment + 16. Body + 17. Electric circuits |
Repair B3-B4/Passat B3-B4 Volkswagen Passat>> Engines>> Diesel engines>> Gear pulley of a camshaft
Removal of a gear pulley of a camshaft is carried out in the following order:
– remove the contact socket of the electromagnetic valve останова the engine;
– remove a belt of a drive of auxiliary units;
– establish the cylinder No. 1 piston in VMT of a step of compression (see подразд. 3.3.3);
– remove a gear belt of a drive of GRM (see подразд. 3.3.4);
– fix a gear pulley 2 (see
fig. 3.65
) a camshaft from a provorachivaniye and unscrew a bolt of 1 fastening of a pulley;
– remove a pulley 2 camshafts.
Installation of a gear pulley of a camshaft is carried out in the following order:
– wipe interfaced surfaces of a pulley and a camshaft;
– establish a segment shponka in a camshaft groove;
– establish a gear pulley 2 (see
fig. 3.65
). If the segment shponka is not used, insert a ledge of a nave of a pulley into a camshaft flute;
– establish a gear belt of a drive of GRM (see подразд. 3.3.4);
– check combination of all adjusting labels: a flywheel (see
fig. 3.61
), a gear pulley of a camshaft (see
fig. 3.5
) and a gear pulley of TNVD
(fig. 3.67)
;
– establish covers 19 and 20 (see
fig. 3.64
) GRM drive;
– establish a pulley 2 cranked shaft;
– establish a belt 3 drives of auxiliary units and adjust its tension.
|
|